Q.61
10 Jul 2024 Shift 155 workers can finish a work in 16 days. For finishing the same work in 10 days, how many more workers are required?
Show answer without attempting
Answer: C — 33
Open question pageSSC CHSL · Quantitative Aptitude · 1,912 questions
1,912 Arithmetic questions asked in SSC CHSL previous year papers, each with the correct answer and an explanation. Part of Quantitative Aptitude. Pick an option on any question to practise it.
Page 4 of 96 · Q61–80
Answer: C — 33
Open question pageAnswer: A — 1
Open question pageAnswer: B — 11.54 km/hr
Open question pageAnswer: B — 36
Open question pageAnswer: B — 12500
Open question pageAnswer: C — 27,000
Open question pageAnswer: C — 154
Open question pageAnswer: D — A by 6.25%
Open question pageAnswer: C — 800 m
Open question pageAnswer: A —
Open question pageAnswer: B — 28 : 45
Open question pageAnswer: C — ₹5,779
Open question pageAnswer: B — 25%
Open question pageAnswer: C — 5
Open question pageAnswer: D — A and D are equal.
Open question pageAnswer: B —
Open question pageAnswer: D — 8
Open question pageAnswer: A — 1,490
Open question pageAnswer: A — ₹1,500, 12%
Open question pageAnswer: D —
Open question page0/200 correct0 marks