RRB Group D 28 Nov 2025 Shift 2 — Question 37 (Arithmetic)

Medium2025
A can complete a piece of work in 77 days. B is 75% less efficient than A. C is 40% more efficient than B. If B and C work together for 30 days, A alone will complete the remaining work in:

Answer & explanation

Show the answer

Correct answer: D — 59 days

Let A's 1-day work = 1/771/77. B is 75% less efficient than A, so B's efficiency = 0.25×(1/77)=1/3080.25 \times (1/77) = 1/308. C is 40% more efficient than B, so C's efficiency = 1.40×(1/308)=7/1540=1/2201.40 \times (1/308) = 7/1540 = 1/220. Combined 1-day work of B and C = 1308+1220=5+71540=121540=3385\frac{1}{308} + \frac{1}{220} = \frac{5+7}{1540} = \frac{12}{1540} = \frac{3}{385}. In 30 days, work done by B and C = 30×3385=90385=187730 \times \frac{3}{385} = \frac{90}{385} = \frac{18}{77}. Remaining work = 1−1877=59771 - \frac{18}{77} = \frac{59}{77}. Time taken by A alone to finish remaining work = 59/771/77=59\frac{59/77}{1/77} = 59 days.

From the RRB Group D 28 Nov 2025 Shift 2 paper

This is question 37 of the RRB Group D 28 Nov 2025 Shift 2 question paper (Mathematics, Arithmetic).

More Arithmetic questions

All RRB Group D Arithmetic questions