RRB Group D 28 Nov 2025 Shift 2 — Question 48 (Arithmetic)
A and B working together can do a piece of work in 4 days. B alone can do the same work in 8 days. How long (in days) will A alone take to do double the work?
Answer & explanation
Show the answer
Correct answer: C — 16
1-day work of A and B = . 1-day work of B alone = . 1-day work of A alone = . Time taken by A alone to do 1 unit of work = 8 days. Therefore, to do double the work (2 units), A takes days.
From the RRB Group D 28 Nov 2025 Shift 2 paper
This is question 48 of the RRB Group D 28 Nov 2025 Shift 2 question paper (Mathematics, Arithmetic).
More Arithmetic questions
- If m and n are positive integers and $(m - n)$ is an even number, then $(m^2 - n^2)$…
- Find the simple interest (in ₹) on ₹2,000 at 7% per annum rate of interest for the…
- A train of length 282 m takes 12 seconds to pass over another train 248 m in length…
- An item with a marked price of ₹657 was sold for ₹526. What was the percentage of…
- Five years ago, Meera was three times as old as her niece, Kavya. Seven years from now,…
- A cistern has two inlet pipes, A and B, and one outlet pipe, C. Pipe A can fill the…