MCQ · 2 marks · Scheduling

GATE CS 2012 CS — Q31

Consider the 3 processes, P1, P2 and P3 shown in the table.
ProcessArrival timeTime Units Required
P105
P217
P334
The completion order of the 3 processes under the policies FCFS and RR2 (round robin scheduling with CPU quantum of 2 time units) are
Select one option