SSC CHSL 15 Mar 2023 Shift 4 — Question 70 (Arithmetic)

Easy2023
PP, QQ and RR can complete a work alone in 1212, 1515 and 2020 days respectively. They started the work together. PP left the work 88 days before the work was completed and QQ left the work 55 days after PP had left. RR completed the remaining work alone. How many days will be required to complete the whole work?