SSC CHSL 3 Jul 2024 Shift 3 — Question 58 (Arithmetic)

Easy2024
A and B can complete a piece of work in 12 days. B and C can complete the same work in 15 days and C and A in 10 days. How many days will A take to complete the work by himself?