SSC CGL 27 Jul 2023 Shift 3 — Question 62 (Arithmetic)
40 men can complete a work in 30 days. However, if 10 men leave the group, how many days will the group take to complete the work?
Answer & explanation
Show the answer
Correct answer: A — 40
From the SSC CGL 27 Jul 2023 Shift 3 paper
This is question 62 of the SSC CGL 27 Jul 2023 Shift 3 question paper (Quantitative Aptitude, Arithmetic).