SSC CGL 27 Jul 2023 Shift 2 — Question 55 (Arithmetic)
Ram and Ramesh can do a work in 12 days, Ramesh and Somesh in 15 days and Somesh and Ram in 10 days. If Ram, Ramesh and Somesh work together, in how many days will they complete the work?
Answer & explanation
Show the answer
Correct answer: B — 8
From the SSC CGL 27 Jul 2023 Shift 2 paper
This is question 55 of the SSC CGL 27 Jul 2023 Shift 2 question paper (Quantitative Aptitude, Arithmetic).