RRB Group D 9 Dec 2025 Shift 3 — Question 48 (Arithmetic)
A group of 10 women can weave a designer saree in 20 days. After 4 days, another group of 20 women joins them to work on the same saree. In how many more days will the saree be completely woven?
Answer & explanation
Show the answer
Correct answer: A —
Total work = woman-days. Work done in the first 4 days by 10 women = woman-days. Remaining work = woman-days. After 4 days, total women = women. Time required to finish remaining work = days.
From the RRB Group D 9 Dec 2025 Shift 3 paper
This is question 48 of the RRB Group D 9 Dec 2025 Shift 3 question paper (Mathematics, Arithmetic).
More Arithmetic questions
- If m and n are positive integers and $(m - n)$ is an even number, then $(m^2 - n^2)$…
- Find the simple interest (in ₹) on ₹2,000 at 7% per annum rate of interest for the…
- A train of length 282 m takes 12 seconds to pass over another train 248 m in length…
- An item with a marked price of ₹657 was sold for ₹526. What was the percentage of…
- Five years ago, Meera was three times as old as her niece, Kavya. Seven years from now,…
- A cistern has two inlet pipes, A and B, and one outlet pipe, C. Pipe A can fill the…