RRB Group D 14 Dec 2025 Shift 1 — Question 32 (Arithmetic)
In a presentation competition, group Leo can complete a task in 9 days, while group Tiger can complete it in 18 days. If both groups work together, in how many days will they complete the work?
Answer & explanation
Show the answer
Correct answer: B — 6 days
Group Leo's 1-day work = 1/9, Group Tiger's 1-day work = 1/18. Combined 1-day work = 1/9 + 1/18 = 3/18 = 1/6. Therefore, working together, they will complete the work in 6 days.
From the RRB Group D 14 Dec 2025 Shift 1 paper
This is question 32 of the RRB Group D 14 Dec 2025 Shift 1 question paper (Mathematics, Arithmetic).
More Arithmetic questions
- If m and n are positive integers and $(m - n)$ is an even number, then $(m^2 - n^2)$…
- Find the simple interest (in ₹) on ₹2,000 at 7% per annum rate of interest for the…
- A train of length 282 m takes 12 seconds to pass over another train 248 m in length…
- An item with a marked price of ₹657 was sold for ₹526. What was the percentage of…
- Five years ago, Meera was three times as old as her niece, Kavya. Seven years from now,…
- A cistern has two inlet pipes, A and B, and one outlet pipe, C. Pipe A can fill the…