RRB Group D 28 Nov 2025 Shift 3 — Question 27 (Arithmetic)
Paul, Ryan and Max can finish a certain piece of work in 15, 14 and 21 days, respectively. All three of them started the work together. Paul left the work after 5 days and Ryan left just 3 days before the work was completed. Find the total number of days taken for the work to be completed.
Answer & explanation
Show the answer
Correct answer: C — 7.4
Let total work = 420 units (LCM of 15, 14, 21). Rates: Paul = 28 units/day, Ryan = 30 units/day, Max = 20 units/day. Let total days be . Paul works for 5 days ( units). Ryan leaves 3 days before the end, so he works for days. Max works for all days. Total work equation: days.
From the RRB Group D 28 Nov 2025 Shift 3 paper
This is question 27 of the RRB Group D 28 Nov 2025 Shift 3 question paper (Mathematics, Arithmetic).
More Arithmetic questions
- If m and n are positive integers and $(m - n)$ is an even number, then $(m^2 - n^2)$…
- Find the simple interest (in ₹) on ₹2,000 at 7% per annum rate of interest for the…
- A train of length 282 m takes 12 seconds to pass over another train 248 m in length…
- An item with a marked price of ₹657 was sold for ₹526. What was the percentage of…
- Five years ago, Meera was three times as old as her niece, Kavya. Seven years from now,…
- A cistern has two inlet pipes, A and B, and one outlet pipe, C. Pipe A can fill the…