RRB Group D 28 Nov 2025 Shift 3 — Question 27 (Arithmetic)

Medium2025
Paul, Ryan and Max can finish a certain piece of work in 15, 14 and 21 days, respectively. All three of them started the work together. Paul left the work after 5 days and Ryan left just 3 days before the work was completed. Find the total number of days taken for the work to be completed.

Answer & explanation

Show the answer

Correct answer: C — 7.4

Let total work = 420 units (LCM of 15, 14, 21). Rates: Paul = 28 units/day, Ryan = 30 units/day, Max = 20 units/day. Let total days be xx. Paul works for 5 days (5×28=1405 \times 28 = 140 units). Ryan leaves 3 days before the end, so he works for (x−3)(x-3) days. Max works for all xx days. Total work equation: 140+30(x−3)+20x=420  ⟹  140+30x−90+20x=420  ⟹  50x+50=420  ⟹  50x=370  ⟹  x=7.4140 + 30(x-3) + 20x = 420 \implies 140 + 30x - 90 + 20x = 420 \implies 50x + 50 = 420 \implies 50x = 370 \implies x = 7.4 days.

From the RRB Group D 28 Nov 2025 Shift 3 paper

This is question 27 of the RRB Group D 28 Nov 2025 Shift 3 question paper (Mathematics, Arithmetic).

More Arithmetic questions

All RRB Group D Arithmetic questions