MCQ · 2 marks · Scheduling
GATE CS 2022 CS — Q42
Consider four processes , , , and scheduled on a CPU as per round robin algorithm with a time quantum of 4 units. The processes arrive in the order , , , , all at time . There is exactly one context switch from to , exactly one context switch from to , and exactly two context switches from to . There is no context switch from to . Switching to a ready process after the termination of another process is also considered a context switch. Which one of the following is NOT possible as CPU burst time (in time units) of these processes?