Ratios and Percentages questions

Q65

GATE CS 2013 CSQuantitative AptitudeMCQ2 marks−2/3 if wrong
The current erection cost of a structure is Rs. 13,200. If the labour wages per day increase by 1/5 of the current wages and the working hours decrease by 1/24 of the current period, then the new cost of erection in Rs. is
Show answer without attempting

Answer: B