Q.101
12 Dec 2025 Shift 2Show answer without attempting
Answer: B — 3
A's 1-day work = 1/2, B's = 1/6, C's = 1/3. Combined 1-day work = 1/2 + 1/6 + 1/3 = (3 + 1 + 2)/6 = 6/6 = 1 work per day. Working together, they finish 1 work in 1 day. To do thrice the work (3 units), they will take 3 × 1 = 3 days.