Let total work be LCM(10, 47, 24). Wait, 10, 47, 24: LCM = 2820. Let's use 1 unit per day rates: Nick's rate 1/10, Kevin's rate 1/47, Joe's rate 1/24. Let total days be T. Nick worked for 2 days, so work done by Nick = 2×101=51. Kevin left 5 days before completion, meaning Kevin worked for T−5 days. Joe worked for the entire duration T. Equation: 102+47T−5+24T=1. Let's test option B (T=14.4): 51+479.4+2414.4=0.2+0.2+0.6=1.0. This perfectly satisfies the equation! Thus, the total time is 14.4 days.