Q.41
5 Dec 2025 Shift 3Show answer without attempting
Answer: B — 69 days
Let total work = 90 units. A's efficiency = 1 unit/day. B is 75% less efficient than A, so B's efficiency = 0.25 unit/day. C is 80% more efficient than B, so C's efficiency = 0.25 × 1.8 = 0.45 unit/day. Combined efficiency of B and C = 0.25 + 0.45 = 0.70 unit/day. Work done by B and C in 30 days = 0.70 × 30 = 21 units. Remaining work = 90 - 21 = 69 units. Time taken by A alone to finish remaining work = 69/1 = 69 days.