Q.141
11 Aug 2021 Shift 1X can complete half of the work in 20 days and Y can do one-fifth of the same work in 10 days. X started the work and left after 8 days. Then Y took over to complete the remaining work. The total number of days taken by them to complete the work is:
Show answer without attempting
Answer: D — 48 days