Time & Work questions

Q.1

11 Jul 2024 Shift 1
Nirmal completed the school project in 45 days. How many days will Amit take to complete the same work if he is 25% more efficient than Nirmal?
Show answer without attempting

Answer: C — 36

Open question page

Q.2

11 Jul 2024 Shift 2
Mira can complete a piece of work in 20 days, Nina in 30 days and Sima in 40 days. Mira and Sima worked together for 4 days and then Mira was replaced by Nina. In how many days, altogether, was the work completed?
Show answer without attempting

Answer: C — 16

Open question page

Q.3

11 Jul 2024 Shift 3
Teena does half of a task in 6 days. Later, with Shyam’s help, she completes the remaining work in 4 days. Shyam alone can finish the entire work in:
Show answer without attempting

Answer: D — 24 days

Open question page

Q.4

11 Jul 2024 Shift 4
X, Y and Z can do a work in 24 days, 5 days and 12 days, respectively. In how many days can they do the same work if they work together?
Show answer without attempting

Answer: B — 31133\frac{1}{13} days

Open question page

Q.5

10 Jul 2024 Shift 1
To finish a work, P takes half of the number of days required by Q to finish it. If they together can finish the work in 36 days, then in how many days Q alone can finish the work?
Show answer without attempting

Answer: D — 108

Open question page

Q.6

10 Jul 2024 Shift 1
55 workers can finish a work in 16 days. For finishing the same work in 10 days, how many more workers are required?
Show answer without attempting

Answer: C — 33

Open question page

Q.7

10 Jul 2024 Shift 2
P and Q can do a work in 12 days and 9 days, respectively. They both worked together and earned ₹63,000. The share of P (in ₹) is:
Show answer without attempting

Answer: C — 27,000

Open question page

Q.8

10 Jul 2024 Shift 3
Reena and Riya together can complete a piece of work in 36 days. Riya and Geeta together can complete it in 54 days. Reena and Geeta together can complete it in 81 days. In how many days can Reena alone complete the work?
Show answer without attempting

Answer: D — 9247 days92 \frac{4}{7} \text{ days}

Open question page

Q.9

10 Jul 2024 Shift 4
P completes a work in 12 days and Q in 24 days. In how many days P and Q working together can complete the same work?
Show answer without attempting

Answer: D — 8 days

Open question page

Q.10

9 Jul 2024 Shift 1
Rohan can alone finish a work in 12 days and Hari can alone in 16 days. They both work for 3 days and then Rohan left. After that only Hari works and finishes the work. The total work will be completed in:
Show answer without attempting

Answer: C — 12 days

Open question page

Q.11

9 Jul 2024 Shift 2
30 men working 5 hours a day can do work in 18 days. In how many days will 20 men working 7 hours a day do the same work?
Show answer without attempting

Answer: A — 192719\frac{2}{7}

Open question page

Q.12

9 Jul 2024 Shift 3
If 6 engineers can complete a work in 5 days and 5 skilled workers can complete the same work in 7 days, then the time taken (in days) to complete the same work by 7 engineers and 4 skilled workers will be:
Show answer without attempting

Answer: B — 264732\frac{64}{73}

Open question page

Q.13

9 Jul 2024 Shift 4
A can finish a piece of work by working alone in 4 days. B, while working alone, can finish the same work in 12 days. If both of them work together, then in how many days will the work be completed?
Show answer without attempting

Answer: C — 3

Open question page

Q.14

8 Jul 2024 Shift 1
Antony and Julie can simultaneously complete a work of floor decoration in 15 days and Julie alone in 20 days. In how many days can Antony alone complete the work of floor decoration?
Show answer without attempting

Answer: C — 60

Open question page

Q.15

8 Jul 2024 Shift 2
Rohan takes 10 hours to mow a large lawn. He and Mohan together can mow it in 4 hours. How long will Mohan take to mow the lawn if he works alone?
Show answer without attempting

Answer: C — 203\frac{20}{3} hours

Open question page

Q.16

8 Jul 2024 Shift 3
R and S can finish a work in 10 days, S and T can finish it in 12 days and T and R can finish in 8 days. In how many days will the work be finished if they all work simultaneously?
Show answer without attempting

Answer: B — 24037\frac{240}{37}

Open question page

Q.17

8 Jul 2024 Shift 3
R can finish a work in 6 days if he works 10 hours a day. S can finish it in 5 days if he works 8 hours a day. If both start a work and work daily for 6 hours, the work will be finished in _____ days.
Show answer without attempting

Answer: B — 4

Open question page

Q.18

8 Jul 2024 Shift 4
Tanvi can do a work in 25 days, and Tai can complete the same work in 30 days. They started the work together for 5 days. How much work is left?
Show answer without attempting

Answer: D — 1930\frac{19}{30}

Open question page

Q.19

5 Jul 2024 Shift 1
Sapna finishes a job in 12 hours working alone. If Sapna and Riya finish the same job in 8 hours working together at their respective constant rates, then, in how many hours can Riya do the job working alone?
Show answer without attempting

Answer: D — 24

Open question page

Q.20

5 Jul 2024 Shift 2
Shobhita can complete a painting work in 20 hours while Saroj can complete the same work in 15 hours. In how much time (in hours) can the entire work of painting be completed, if both Shobhita and Saroj work simultaneously?
Show answer without attempting

Answer: C — 8478 \frac{4}{7}

Open question page