Q.1

10 Jun 2022 Shift 1
40 men can complete a piece of work in 18 days. 9 days after they start working together, 5 more men join them. How many days will they now take to complete the remaining work?
Show answer without attempting

Answer: B — 8 days

Open question page

Q.2

10 Jun 2022 Shift 2
A and B together can finish a job in 40 days. A can do the same job on her own in 60 days. How long will B take to do the three-fourth of the same work all alone?
Show answer without attempting

Answer: A — 90 days

Open question page

Q.3

10 Jun 2022 Shift 3
45 people can repair a road in 10 days, working 6 hours a day. In how many days can 30 people, working 6 hours a day, complete the same work?
Show answer without attempting

Answer: D — 15

Open question page

Q.5

9 Jun 2022 Shift 2
If 15 boys earn ₹900 in 5 days, then how much will 20 boys earn in 7 days?
Show answer without attempting

Answer: B — ₹1,680

Open question page

Q.6

9 Jun 2022 Shift 3
3 men and 7 women can complete a task in 10 days. On the other hand, 4 men and 6 women, take 8 days to complete the same task. How long will it take 10 women to complete the same task?
Show answer without attempting

Answer: D — 40 days

Open question page

Q.7

8 Jun 2022 Shift 1
X does a work in 6 days, while Y does it in 12 days. If they work alternatively and X begins, in how many days will the work be finished?
Show answer without attempting

Answer: C — 8

Open question page

Q.8

8 Jun 2022 Shift 2
A, B and C can do a work in 5 days, 6 days and 10 days, respectively. Working together, in how many days will they finish the same work?
Show answer without attempting

Answer: A — 2172\frac{1}{7}

Open question page

Q.9

8 Jun 2022 Shift 3
If Priya and Renu can do a job in 12 hours (working together at their respective constant speeds) and Priya can do the job alone in 18 hours, in how many hours can Renu do the job alone?
Show answer without attempting

Answer: A — 36

Open question page

Q.10

7 Jun 2022 Shift 1
Raghav and Aditya can complete a work in 3 days. Aditya and Ishaan can complete the same work in 4 days. Ishaan and Raghav can complete it in 6 days. How many days will it take for Raghav, Aditya and Ishaan, combined together, to complete the same amount of work?
Show answer without attempting

Answer: D — 2232\frac{2}{3}

Open question page

Q.11

7 Jun 2022 Shift 2
Tim is thrice as good a workman as Joya and together they finish a piece of work in 75 days. In how many days will Tim alone finish the work?
Show answer without attempting

Answer: B — 100 days

Open question page

Q.12

7 Jun 2022 Shift 3
Pranjal takes twice as much time as Vikram or thrice as much time as Ashwin to finish a piece of work. Working together, they can finish the work in 6 days. Vikram can do the work alone in:
Show answer without attempting

Answer: A — 18 days

Open question page

Q.14

6 Jun 2022 Shift 2
A work is done by P & Q, Q & R, and R & P in 12, 15, and 20 days, respectively. How many days will P alone take to complete the work?
Show answer without attempting

Answer: D — 30 days

Open question page

Q.16

6 Jun 2022 Shift 3
A can complete a work in 5 days and B can complete the same work in 10 days. If A and B work alternately, starting with A, in how many days will they complete the work?
Show answer without attempting

Answer: B — 6126\frac{1}{2} days

Open question page

Q.17

3 Jun 2022 Shift 1
Manoj and his wife Swathi fill a tank with water fetched from a well. Manoj fetches 5 litres of water in 4 minutes whereas Swathi fetches 4 litres of water in 5 minutes. Find the time taken by them together to fetch 205 litres of water.
Show answer without attempting

Answer: C — 100 minutes

Open question page

Q.18

3 Jun 2022 Shift 2
In one-sixth of the time that B takes to complete a piece of work, A can complete half of the same work. If working together they take 16 days to complete the work, how much time shall B take to complete it alone?
Show answer without attempting

Answer: D — 64 days

Open question page

Q.19

3 Jun 2022 Shift 3
Ram and Shawan working together can complete a job in 5 hours, where as Ram alone can complete the same job in 6 hours. In how many hours can Shawan alone complete the job?
Show answer without attempting

Answer: A — 30

Open question page

Q.20

2 Jun 2022 Shift 1
A is 3 times as fast as B and is, therefore, able to complete a work in 32 days lesser than B. A and B, working together, can complete the work in _________.
Show answer without attempting

Answer: B — 12 days