Time & Work questions

Q.61

3 Aug 2023 Shift 2
Babita is 1.25 times as efficient as Deepak. Working together the duo can complete a piece of work in 40 days. In how many days can Deepak alone complete the same piece of work?
Show answer without attempting

Answer: B — 90

Open question page

Q.62

3 Aug 2023 Shift 2
A contractor employed 69 workers to complete a work in 20 days. How many more workers he should employ to complete the work in 12 days?
Show answer without attempting

Answer: B — 46 workers

Open question page

Q.63

2 Aug 2023 Shift 1
A can finish a work in 15 days, B can finish the same work in 25 days. They work together for 5 days. The rest of the work is finished by A and C in 4 days. Then C alone can finish the work in:
Show answer without attempting

Answer: C — 20 days

Open question page

Q.64

2 Aug 2023 Shift 3
A and B can do a piece of work in 10 days and 15 days, respectively. They worked together, but 5 days before the completion of the work, A left. In how many days was the work completed?
Show answer without attempting

Answer: D — 9

Open question page

Q.65

2 Aug 2023 Shift 4
A can do a piece of work in 12 days and B can do the same work in 15 days. If both do the work together, then in how many days will the work be completed?
Show answer without attempting

Answer: B — 6236 \frac{2}{3}

Open question page

Q.66

21 Mar 2023 Shift 1
A can complete 3/8 part of a work in 36 days. B can complete 1/2 part of the same work in 27 days. Which of the following statement(s) is/are correct? I. A is less efficient than B. II. A and B working together can complete 11/15 part of the same work in 36 days.
Show answer without attempting

Answer: B — Only I

Open question page

Q.67

21 Mar 2023 Shift 2
A and B together can complete a work in 20 days. A is 20 percent more efficient than B. B alone can complete the same work in how many days?
Show answer without attempting

Answer: C — 44 days

Open question page

Q.68

21 Mar 2023 Shift 3
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs.1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?
Show answer without attempting

Answer: D — Rs.500

Open question page

Q.69

21 Mar 2023 Shift 4
To complete a wall, X takes 50 percent more time than Y. If together they complete the wall in 15 days, then how much time will X alone take to complete it?
Show answer without attempting

Answer: C — 37.5 days

Open question page

Q.70

20 Mar 2023 Shift 1
A certain number of persons can complete a work in 90 days. If there be 10 persons less, it would have taken 10 days more for the work to be completed. Find the total number of persons in the beginning.
Show answer without attempting

Answer: D — 100

Open question page

Q.71

20 Mar 2023 Shift 3
A and B together can complete a work in 20 days. B and C together can complete the same work in 15 days. If A, B and C all work together, then the same work gets completed in 10 days. How many days will A and C together take to complete the same work?
Show answer without attempting

Answer: D — 12 days

Open question page

Q.72

20 Mar 2023 Shift 4
A alone can complete a work in 20 days with full efficiency. If the efficiency of A decreases by 20 percent, then A alone can do the same work in how many days?
Show answer without attempting

Answer: C — 25

Open question page

Q.73

17 Mar 2023 Shift 1
A alone can complete a work in 40 days. 20 percent of the same work will be completed by A in how many days?
Show answer without attempting

Answer: A — 8 days

Open question page

Q.74

17 Mar 2023 Shift 2
Rani can do a work in 10 days10\text{ days}. Priya can do the same work in 15 days15\text{ days} and Guddu can do the same work in 12 days12\text{ days}. If they do that work together and they are paid Rs. 90009000, then what is the share of Priya?
Show answer without attempting

Answer: A — Rs. 24002400

Open question page

Q.75

17 Mar 2023 Shift 3
S does half as much work as T in 1/8 of the time taken by T. If they together complete a work in 60 days, then how may days shall S alone take to complete that work?
Show answer without attempting

Answer: C — 75 days

Open question page

Q.76

17 Mar 2023 Shift 4
Rama alone can do a work in 3 days working 4 hours a day. Seema alone can do the same work in 3 days working 10 hours a day. How many hours do they need to work together in a day to complete the same work in 6 days?
Show answer without attempting

Answer: D — 2 hours

Open question page

Q.77

16 Mar 2023 Shift 1
44 men and 77 women can do a work in 88 days. 77 men and 44 women can do the same work in 55 days. Find the number of days in which 88 women can finish the work.
Show answer without attempting

Answer: B — 55 Days55\text{ Days}

Open question page

Q.78

16 Mar 2023 Shift 3
88 men or 1010 boys can complete a work in 174174 days. 1212 men and 1414 boys will complete the same work in how many days?
Show answer without attempting

Answer: A — 60 days60\text{ days}

Open question page

Q.79

16 Mar 2023 Shift 4
A work can be completed by 8 boys in 48 days. If 2 boys leave after working for 24 days, then how many days will be needed to complete the remaining work?
Show answer without attempting

Answer: C — 32 days

Open question page

Q.80

15 Mar 2023 Shift 1
Rahul alone can complete a work in 10 days10\text{ days} and Sonu alone can complete the same work in 15 days15\text{ days}. If they work together for 4 days4\text{ days}, then what part of total work is left?
Show answer without attempting

Answer: D — 1/3

Open question page